If you want to assume % Work Complete is the same as % Complete, you can configure it in : However, most scheduler consider % Work Complete equal to % Complete to make it easier. In fact, % Work Complete is not always the same as % Complete. One hundred percent Work means workers spend 16 hours doing work. For example, workers have to do work for two days, with the number of work hours per day being 8 hours, so the total Work is 16 hours. % Work Complete(if you have a resource): is the percentage of work done by the resource (in hours).By updating % Complete, the updated activity remaining duration is automatically calculated according to the percentage of the remaining work compared to the overall duration of the job. % Complete : is activity progress (in percentage).